Building Estimate page 4

Method Of Individual Work Estimate
General item of work required for Building Estimate

Earthwork In Filling or Sand Filling
(unit in cum)
Definition: 
The excavated earth from foundation trench used for filling is called Earthwork in filling. 
Consist of two parts- 
1. For foundation trench filling, 
2. For plinth filling

Some Important Equation:

  • Foundation trench filling = 1/5th of Earthwork in excavation. 
  • Plinth filling = Carpet area x Depth of filling

During Construction Work: 
  • After Foundation or Substructure work Completely done we start filling.
  • The material of filling free from lumps, Vegetation, Chemical and Organic Material.
  • Filling of sand in a layer of 250mm and compacting with water (Hand Rammer weight 7 to 10 Kg).


Share:

No comments:

Post a Comment

Definition List

Popular Posts

This Blog is protected by DMCA.com

Ads

Labels

Get Email Notification

Enter your email address:

Delivered by FeedBurner

Civil Engineering Connect

Girl in a jacketGirl in a jacket