Different types of Building Estimates
Quantities, Rates, and Cost of all individual items calculated from Drawing and measurement sheets, And prepared Details and most Accurate sheets.
All multiplying dimensions are shown in details estimations.
All multiplying dimensions are shown in details estimations.
Approximate Estimate (Rough Estimate):
In this types of the estimate, we get approximate cost in a short time.
Approximate cost find out by similar typical types of estimates. Using such guided parameter which like Plinth area.
A Quantity Estimate (Quantity Survey):Approximate cost find out by similar typical types of estimates. Using such guided parameter which like Plinth area.
This estimate is also known as Bill of quantity (BOQ). It is a list of items of work which multiplying with the unit rates of individual work and lastly shown the total work of the project and project cost.
Only Quantity, Rates and cost is shown in this estimations.
Only Quantity, Rates and cost is shown in this estimations.
Revised Estimate:
Due changes in unit rates the sanctioned amount is exceeded. This estimate is a details estimate for revised quantities and rates of item.
So no additions or revisions of drawing is necessary.
So no additions or revisions of drawing is necessary.
Supplementary Estimate:
Due Addition and changes of work the sanctioned amount is exceeded. This estimate is a details estimate for revised quantities and rates of items.
Here, Additions or revisions of drawing is necessary.
Here, Additions or revisions of drawing is necessary.